SMOV STATUS & PLANNING MEETING - 5 MAY 97 http://www.stsci.edu/smov/ NOTE: The next meeting is May 12, 8:30 AM. By general consensus, these SMOV Status & Planning Meetings will be reduced in frequency to once per week, on Mondays at 8:30 a.m. for the month of May. Starting in June, planning and scheduling meetings will revert to the normal Tuesday morning PRESTO "OPM" that will have SMOV scheduling requirements as an input. SMOV status & planning meetings will then be held as needed with a smaller group of participants. In the 77 days starting from the day before Release, we have had 44 SMOV Status and Planning Meetings. THANKS TO EVERYONE WHO HAS SUPPORTED THESE MEETINGS WITH THEIR TIME AND TECHNICAL INPUTS. THE EFFORT HAS BEEN A MAJOR FACTOR IN SMOV'S SUCCESS TO DATE. STATUS REPORTS 1. Observatory Status - SI - An HSTAR concerning a status buffer message for a NICMOS filter wheel retry was generated. The filter motion in question was the F110W-to-blank. The flight software load 4.07, scheduled for installation today, is in part designed to alleviate the conditions that cause retries and to eliminate the status buffer message as a response to retries. All other systems nominal. 2. WFPC2 Status - Proceeding nominally with Cycle 6 science and remaining SMOV monitors. 3. NICMOS Status - Engineering Status Today's temps: Detector 1 Mounting Cup temperature is stable at 61.14 degK. VCS temperature is 99.1 degK and continues to show an temperature increase of about 0.2 degK/day. - Science Status - Nothing new to report. 4. STIS Status - Engineering Status The MAMA high-voltage testing (7105) continued nominally on Sunday. The NUV MAMA was ramped to -1750 volts and everything looked nominal. MAMA dark rates seemed marginally higher than Band 1 measurements, isolated preferentially to a bottom corner of the detector. Analysis is in preliminary stages and more info will be available at a separate meeting later today. The next step is May 7 with a full ramp-up of the NUV MAMA. The CCD is operating nominally after being brought back on line Friday, following last weeks CEB partial reset (See notes from 2 May.). - Science Status This week's visit of the CCD peak-up test 7071 appears to have gone well, although scientific analysis is not yet complete. In the point source acquisition portion of the test, the filter offset was correctly applied. If this visit is deemed successful, there will most likely be no need to reschedule last week's visit lost to the CEB partial reset. The ERO 7130 (GL229B) was reported to have produced good results. 5. FGS status - FRR for FGS-1R commissioning occurred on Thursday, 1 May, @GSFC and confirmed the plans to proceed with using FGS-1R as a third guider starting in SMS139. Alignment matrices for FGS-1R only will be implemented at this time. 6. FOC/COSTAR status- The FOC SMOV program is complete. The SMOV TTRB has enabled the resumption of FOC science. PLANNING REPORTS 1. Status of Upcoming SMSs - SMS125 - Currently executing. - SMS132 - Updates for the STIS CCD Bad Pixel Table are expected late today or early tomorrow prior to Final Mode products being made available for review. - SMS139 - SARs went out over the weekend. Initial Mode products are expected by tomorrow morning. Will contain regular MAMA operations and the first use of FGS-1R as a guider. The MAMA rules for SAA avoidance are in place. The MAMA operations in this SMS are being scheduled in the SAA-free orbits, while the CCD and NICMOS activities are being fit into the SAA-impacted orbits. A DF 224 FSW load is also scheduled for installation during the exectution period of this SMS. - SMS146 - Calendar building starting today. 2. Replans STIS - No significant replans at this time. NICMOS - No significant replans have yet been identified. OPERATIONS STATUS 1. OPUS - No new problems to report. OPUS will be down for a time today during software installation of OPUS 6.3. 2. Archive - No new problems to report.
Go back to the Meeting Minutes Page