SMOV STATUS & PLANNING MEETING - 21 APR. 97 http://www.stsci.edu/smov/ NOTE: The next meeting is April 23, 8:30 AM. STATUS REPORTS 1. Observatory Status - All systems nominal. Weekend HSTARs: 1. A NICMOS Filter Wheel 3 Retry occurred on day 109. The retry was successful. 2. A STIS bulkhead 6 temperature went out of limits low for a short time. The limit is -15C and it is currently back in limits at 14.8. This is understood to be related to abnormally cold conditions because the MAMA LVPSs are off. 3. On 110/2028z, four status buffer messages were reported when the number of images in the NICMOS buffer exceeded 100. It may have resulted in some data loss to the 7046 Internal Flats & Transfer Stability activity, but this has not been determined for sure yet. The problem continues to be investigated. Glenn Schneider also took the action to touch base with John Campbell after the meeting. Gyro 1 tests on Friday looked good and further VEST testing is scheduled for today with plans for its insertion into the control loop later this week. The FRR is scheduled for noon (EDT) Tues., 22 April. Pete Pataro reports that there will be outages today and tomorrow for software installations involving NCC and White Sands. No adverse impact to STOCC operations is envisioned. 2. WFPC2 Status - Proceeding nominally with Cycle 6 science and remaining SMOV monitors. 3. NICMOS Status - Engineering Status - No further NICMOS engineering status was reported. - Science Status - Nominal Analyses of the latest Camera 3 focus monitor data (18 April) showed more small movement (~ 0.2mm) of the camera focus back toward nominal. The NICMOS team now reports a small amount of vignetting in all three cameras; about 8 - 10% at the edge of the camera (within 25 pixels of the edge). Except for camera 3, this is a new phenomenon, i.e., within the last several weeks. The limb avoidance (7053) data is being studied and may result in a some favorable revision of the current earth limb avoidance assumptions for NICMOS. The EROs 7119 and 7114 have been taken but not studied in detail yet. 4. STIS Status - Engineering Status - Nominal. - Science Status The 7107 CCD anealing proposal has completed and the effects on hot pixels are being studied. The last two data sets from ERO 7142 have still not been extracted from OPUS. Jim Rose/OPUS to investigate today. Some missing flat field data from 7142 is in OPUS but miss-labelled as wavecal data. OPUS is working to correct. The "re-use target offset" for ERO 7124 did not work correctly. The calculation was for a +3 arcsec shift from the center of slit, but got applied to the -3 arcsec position from the previous visit. The target therefore ended up in the center of the slit. This apparently does not invalidate the ERO data. 5. FGS status - No new activities. SMOV mini-OFADS are scheduled for this week (SMS111). 6. FOC/COSTAR status- The FOC SMOV program is complete. The SMOV TTRB has enabled the resumption of FOC science. PLANNING REPORTS 1. Status of Upcoming SMSs - SMS111 - Currently executing. - SMS118 - Issued a 2nd set of initial mode products that included commanding instructions for MAMA high voltage activation planned for this SMS. Finals will be run later today, and will involve a lot of commanding checks. - The FRR for FSW and installation for MAMA SAA operations is scheduled for Tuesday, 22 April. FSW installation is scheduled for the next day. - SMS125 - The calendar is complete. This SMS will contain the last piece of MAMA HV Turn-On (7105) on day 127 (May 7). - Initial Mode products are planned for later today. - SMS132 - Calendar building will start today. 2. Replans STIS - MAMA HV Turn-on (7105) is currently planned for SMS118. Downstream MAMA scheduling has been assessed. According to the latest plan, regular MAMA SMOV operations are to start in the SMS 139. NICMOS - No significant replans have yet been identified. OPERATIONS STATUS 1. OPUS - Nominal. Previously reported problems continue to be investigated. 2. Archive - Nominal.
Go back to the Meeting Minutes Page