HST INS Work Item Data Sheet

1. SI/Title: WFC3/TV2 and TV3

2. INS Lead: H. Bushouse

3. Description of Work:
Plan the WFC3 Thermal Vacuum Test Science Calibration activities, and
work with GSFC personnel to incorporate those activities into the
overall TV plan. Develop detailed test descriptions, phase II
proposals, and generate and review test SMSs to execute the
observations. Analyze the instrument data and write ISRs describing
the results.

Plan STScI staff support, including the use of additional Data
Analysts, and arrange for the necessary training for those personnel.

4. Schedule Constraints and Dependencies:
TV2 (UVIS) is currently planned for August - Oct 2006, and TV3 (IR) is
planned for January - March 2007.

5. Risks and Open Issues:


6. Priority: High

7. Priority Justification:
TV work is needed for instrument completion and delivery to GSFC.

8. Resources (including estimated calendar duration for each portion):
a. Requirements
WFC3 IPT


b. Development
WFC3 IPT
Commanding Developer
Instrument Engineer

c. Testing
WFC3 IPT
Commanding Developer
Commanding Support
Instrument Engineer
Data Analysts
GSFC SITS Support Personnel

9. Documentation and Deliverables:
Test Descriptions
Phase II Proposals
Test SMSs
WFC3 ISRs