| May 2002 | Call for declaration of interest by potential ALFA users | 
| Jul 2002 | Contract signed with CSIRO for construction of multibeam receiver system | 
| Sep 2002 | Multibeam receiver interface meeting at Arecibo, including discussion of front-end specifications and design | 
| Nov 2002 | Final design of receiver system set. Manufacturing of receiver system begins | 
| Sep 2003 | Feed array manufacture | 
| Dec 2003 | Feed array testing completed | 
| Feb 2004 | Receiver construction completed | 
| Mar 7-22, 2004 | Receiver acceptance tests at CSIRO completed | 
| Mar 22-26, 2004 | Gregorian dome rotary floor refurbishment | 
| Mar 24, 2004 | ALFA Frontend packed-up and shipped from CSIRO to Arecibo | 
| Apr 1, 2004 | ALFA receiver delivered to Arecibo | 
| Apr 1-18, 2004 | ALFA pre-installation testing | 
| Apr 19-20, 2004 | ALFA frontend installation in Gregorian dome | 
| Apr 21, 2004 | ALFA commissioning begins | 
| Aug 2004 | ALFA shared-risk precursor surveys begin | 
| Feb 2005 | Major ALFA surveys begin | 
| Apr 16, 2007 | ALFA removed for telescope painting | 
| Dec 10, 2007 | ALFA reinstalled after painting | 
|   Ready to roll [med] [big] |   Top view [med] [big] |   ALFA's raincoat [med] [big] |   Duct tape rules! [med] [big] | 
|   A new day dawns [med] [big] |   Driving under the dish [med] [big] |   Launch preparations [med] [big] |   Up, up, and away! [med] [big] | 
|   ALFA is lifted through the center of the dish [med] [big] |   A long way to go [med] [big] |   ALFA rising [med] [big] |   ALFA approaches the platform [med] [big] | 
|   The Gregorian dome is driven toward ALFA [med] [big] |   The platform crew take hold of ALFA [med] [big] |   The protective wrapping is removed [med] [big] |   Safely inside the Gregorian dome [med] [big] |