Документ взят из кэша поисковой машины. Адрес
оригинального документа
: http://www.naic.edu/alfa/gen_info/timeline.shtml
Дата изменения: Unknown Дата индексирования: Tue Oct 2 06:20:22 2012 Кодировка: Поисковые слова: ngc 891 |
May 2002 | Call for declaration of interest by potential ALFA users |
Jul 2002 | Contract signed with CSIRO for construction of multibeam receiver system |
Sep 2002 | Multibeam receiver interface meeting at Arecibo, including discussion of front-end specifications and design |
Nov 2002 | Final design of receiver system set. Manufacturing of receiver system begins |
Sep 2003 | Feed array manufacture |
Dec 2003 | Feed array testing completed |
Feb 2004 | Receiver construction completed |
Mar 7-22, 2004 | Receiver acceptance tests at CSIRO completed |
Mar 22-26, 2004 | Gregorian dome rotary floor refurbishment |
Mar 24, 2004 | ALFA Frontend packed-up and shipped from CSIRO to Arecibo |
Apr 1, 2004 | ALFA receiver delivered to Arecibo |
Apr 1-18, 2004 | ALFA pre-installation testing |
Apr 19-20, 2004 | ALFA frontend installation in Gregorian dome |
Apr 21, 2004 | ALFA commissioning begins |
Aug 2004 | ALFA shared-risk precursor surveys begin |
Feb 2005 | Major ALFA surveys begin |
Apr 16, 2007 | ALFA removed for telescope painting |
Dec 10, 2007 | ALFA reinstalled after painting |
Ready to roll [med] [big] |
Top view [med] [big] |
ALFA's raincoat [med] [big] |
Duct tape rules! [med] [big] |
A new day dawns [med] [big] |
Driving under the dish [med] [big] |
Launch preparations [med] [big] |
Up, up, and away! [med] [big] |
ALFA is lifted through the center of the dish [med] [big] |
A long way to go [med] [big] |
ALFA rising [med] [big] |
ALFA approaches the platform [med] [big] |
The Gregorian dome is driven toward ALFA [med] [big] |
The platform crew take hold of ALFA [med] [big] |
The protective wrapping is removed [med] [big] |
Safely inside the Gregorian dome [med] [big] |