sitePwrshutdown 1999

Site power shutdown 1999

10may11

The setup
The  shutdown sequence
430 plots
lband plots
possible rfi

 

 The site power was shutdown on 20jan1999 to test the rfi emitted on site.  I found the datafile (/proj/x111/corfile.20jan99.x111.1) and reduced the lband and 430 data from the dome (after massaging the idl routines so i could read in the old data format). I used tapasi's memo to assign the different scans to different on, off sequences..


The setup:


The  shutdown sequence:

    Everything was turned off (except as noted in (1) below). Things where then switched on,off,on and then left on.

Tapasi's notes on the sequence:


The sequence:

  1.  Everything off, except as Noted in (1) above
    • seq: off, off
  2.  vsq+cafeteria+gate
    • seq: on,off,on
  3.  PANEL board 3 (tower 12, anchor 12, emergency generator)
    • seq:on,off,on
  4. Optical Lab (4):
    • seq.on,only lidar off, on, off2, on2
  5. Seti van
    • seq: on
  6. platform Tie down
    • seq:on,off,on
  7. Platform rotary joint
    • was not turned off because of compressors.
  8. visitor center
    • on,off,on
  9. Building II
    • seq:on floor1,on floor2, on floor3, on floor4 + 2nd flr a/c
  10. VSQ west hill (family units, bachelor units)
    • seq:on,off,on
  11. 50 MHz transmitter
    • seq:on,off,on
  12. Old maintenance line
    • seq:on,off,on
  13. Ware House Machine Shop
    • seq:on,off,on
  14. Ware House and Purchasing
    • seq:on,off,on
  15. Turbine
    • seq:on,off,on

Plotting the dome 430 data

    The processing was:

spectral results 430 dome, all locations vertical scale .04Tsys (.ps) (.pdf)
spectral results 430 dome, all locations vertical scale .2 Tsys (.ps) (.pdf)

lband data

    For the lband plots, i've overplotted polA,and polB in the same colors.

  1.  vsq+cafeteria+gate (.ps) (.pdf)
  2.  PANEL board 3 (tower 12, anchor 12, emergency generator) (.ps) (.pdf)
  3. Optical Lab (4): (.ps) (.pdf)
  4. Seti van (.ps) (.pdf)
  5. platform Tie down (.ps) (.pdf)
  6. visitor center (.ps) (.pdf)
  7. Building II (.ps) (.pdf)
  8. VSQ west hill (family units, bachelor units) (.ps) (.pdf)
  9. 50 MHz transmitte (.ps) (.pdf)
  10. Old maintenance line (.ps) (.pdf)
  11. Ware House Machine Shop (.ps) (.pdf)
  12. Ware House and Purchasing (.ps) (.pdf)
  13. Turbine (.ps) (.pdf)


Possible rfi:


processing: x101/110509/rfisite.pro  plus all the corxxx.pro routines in this directory.