October 22, 2010, at 12:03 PM
by 131.111.48.85 -
Changed lines 1-3 from:
This meeting will take place at 13:30 on Friday 14 May, in the Ryle Seminar Room.
to:
Technical Meeting #3: Software requirements and conceptual design
This meeting took place at 13:30 on Friday 14 May, in the Ryle Seminar Room.
May 14, 2010, at 04:10 PM
by jsy1001 -
Added line 27:
- DFB (TBC): Write down initial latency and frame rate requirements with brief justification
May 14, 2010, at 04:04 PM
by jsy1001 -
Added lines 10-22:
Conclusions
- Very preliminary power budget is as follows:
- Camera cooling 100W
- Computing 150W
- Note: once technical interchange begins need to query actual limits on electrical power available, allowed dissipation within electronics cabinets, and allowed dissipation to chilled fluid being used for electronics cabinets
- A single "standard" computer could run all of the FTT/NA software (under Xenomai)
- However, cable length restrictions could force us to use a 2nd low-power computer near to the Andor camera
- This would require a 2nd temperature-controlled enclosure, so best avoided
- Once technical interchange begins need to query cable routing and whether a dedicated short cable tray can be installed from Q5 to near the camera, to allow use of 1 computer only
- JSY suggested GUI could be a separate application that is started and stopped independently
- EBS prefers C (with threads) ISS interface framework
- Need to think about what combinations of commands might run concurrently and what thread-safety strategy to employ
Added lines 24-26:
- JSY: Define software components and inter-component dataflows (hardware-independent)
- JSY: Ask Chris Mayer for field rotation rate
- EBS: Look for 1U or 2U computers with 2 PCI slots drawing < 150W
May 13, 2010, at 02:19 PM
by jsy1001 -
Changed lines 1-10 from:
This meeting will take place at 13:30 on Friday 14 May, in the Ryle Seminar Room.
to:
This meeting will take place at 13:30 on Friday 14 May, in the Ryle Seminar Room.
Agenda
- FTT/NAS & FLC Software Requirements
- Next steps leading to a conceptual software architecture
Discussion Slides
Slides as PDF
Task Assignments
May 11, 2010, at 06:36 PM
by jsy1001 -
Added line 1:
This meeting will take place at 13:30 on Friday 14 May, in the Ryle Seminar Room.
|