Документ взят из кэша поисковой машины. Адрес оригинального документа : http://www.mrao.cam.ac.uk/projects/OAS/pmwiki/pmwiki.php/MROIFastTipTilt/TechMeet1?action=diff
Дата изменения: Unknown
Дата индексирования: Sat Mar 1 21:48:01 2014
Кодировка:

Поисковые слова: starspots
OptInt PmWiki : Tech Meet 1 | History
Return to Tech Meet 1  (Edit)

MROIFastTipTilt.TechMeet1 History

Hide minor edits - Show changes to markup

April 30, 2010, at 03:14 PM by 131.111.48.85 -
Added line 47:

Source file (requires XMind software)

April 30, 2010, at 03:05 PM by 131.111.48.85 -
Added lines 17-19:

Discussion Slides

Slides as PDF Δ

April 30, 2010, at 03:01 PM by 131.111.48.85 -
Changed line 44 from:

(:includeupload FTT_postTM1.html:)

to:
April 30, 2010, at 02:51 PM by 131.111.48.85 -
Added lines 42-44:

Concept Map

(:includeupload FTT_postTM1.html:)

April 30, 2010, at 02:17 PM by 131.111.48.85 -
Changed lines 3-4 from:

This meeting will take place on Friday 30 April at 10:30 in the Ryle Seminar Room. All team members are invited.

to:

This meeting took place on Friday 30 April at 10:30. Attendees: JSY, MF, CAH, DFB, XS, EBS, ADR, DMAW

Changed lines 19-30 from:
  • EBS: liase with ADR about possible sources for off-axis paraboloids
  • EBS: chase Princeton for mechanical drawings of camera
  • DFB: assign working value for overall image quality requirement
  • DFB: assign range for pixel scale
  • ADR & CAH: think about how to apportion image quality budget
  • ADR & CAH: nominal stability budget
  • XS: understand space envelope, optical components & make CAD drawing
  • XS: initial studies of achievable stability
  • JSY: photon rates
  • MF: get available environmental stats
  • MF: thermal analysis of camera in box
  • DMAW & MF: start thinking about test arrangements
to:

High priority tasks

Need to get results for discussion at next meeting in one week

  • DFB & JSY: Assign working value for overall image quality requirement
    • Note we will use the working value until it can be refined by simulation
  • DFB: Assign range for pixel scale
  • ADR & CAH: Think about how to apportion image quality budget
  • ADR & CAH: Nominal stability budget
  • XS: Understand space envelope, optical components & make CAD drawing
  • XS: Initial studies of achievable stability
  • MF: Thermal analysis of camera in box
  • JSY: Make corrections to appendix of FTT technical requirements document

Lower priority tasks

  • ADR: Optical design using off-the-shelf components
  • EBS: Liase with ADR about possible sources for off-axis paraboloids
  • EBS: Chase Princeton for mechanical drawings of camera
  • JSY: Photon rate calculations
  • MF: Get available environmental statistics as background information
  • DMAW & MF: Start thinking about test arrangements

Next Meeting

A follow-up meeting to discuss initial results from the high priority tasks will take place at 14:00-16:30 on Friday 7 May in the Ryle Seminar Room.

April 30, 2010, at 01:01 PM by 131.111.1.66 -
Added line 29:
  • DMAW & MF: start thinking about test arrangements
April 30, 2010, at 12:58 PM by 131.111.1.66 -
Changed lines 15-28 from:
  • Next meeting(s)
to:
  • Next meeting(s)

Task Assignments

  • EBS: liase with ADR about possible sources for off-axis paraboloids
  • EBS: chase Princeton for mechanical drawings of camera
  • DFB: assign working value for overall image quality requirement
  • DFB: assign range for pixel scale
  • ADR & CAH: think about how to apportion image quality budget
  • ADR & CAH: nominal stability budget
  • XS: understand space envelope, optical components & make CAD drawing
  • XS: initial studies of achievable stability
  • JSY: photon rates
  • MF: get available environmental stats
  • MF: thermal analysis of camera in box
April 29, 2010, at 04:43 PM by 131.111.48.85 -
Added lines 1-15:

Technical Meeting #1: Optomechnical design and derived requirements brainstorm

This meeting will take place on Friday 30 April at 10:30 in the Ryle Seminar Room. All team members are invited.

Agenda

  • Review of top-level requirements
    • Primary functions
    • Environment
    • Space envelope
    • Stability
  • Discussion of possible optical layouts and relevant derived requirements for optomechanics
  • Next steps
    • Tasks
    • Next meeting(s)
Recent Changes (All) | Edit SideBar Page last modified on April 30, 2010, at 03:14 PM Edit Page | Page History
Powered by PmWiki