MROI.ScienceInstrumentDownselect History
Hide minor edits - Show changes to markup
May 04, 2007, at 03:37 PM
by 131.111.48.85 -
May 04, 2007, at 03:36 PM
by 131.111.48.85 -
Changed lines 3-4 from:
to:
May 04, 2007, at 03:31 PM
by 131.111.48.85 -
Changed line 36 from:
to:
May 04, 2007, at 03:24 PM
by 131.111.48.85 -
Changed lines 37-39 from:
to:
The choice of switchyard for each concept also impacts the design of the FT switchyard. See Switchyards.
March 09, 2007, at 05:30 PM
by John Young - Status from 2006/10/12 update (see attachment)
Changed lines 1-30 from:
Workpackage Definition
Milestone | Person(s) | Status |
Beam size memos | DFB | Delivered |
Generic Switchyard Requirements | JC | Delivered |
Devise slide tests | CJ | Complete |
Survey of commercial slides | CP | Complete |
Generic Detector Requirements | JSY | Delivered |
P4S combiner optimization | JC | Complete |
P4S switchyard optimization | JC | Complete |
P8 combiner optimization | JC | Complete |
P8 (internal) switchyard optimization | JC | Complete |
P4/P8 manufacturer dialogue | JC | Due 2006/07/31 |
P4S/P8 spectrograph optimization | CJ | Due 2006/09/01 |
I4S combiner optimization | FB | Due 2006/07/17 |
I4S switchyard optimization | JC | Complete |
I6 combiner optimization | FB | Due 2006/07/17 |
Optical interface with fringe tracker | JC/CJ | Due 2006/08/14 |
Slide tests Phase 1 (1 slide, tip-tilt repeatability) | CP | Due 2006/08/14 |
Spatial filter evaluation | MCE | Due 2006/09/11 |
Alignability evaluation | JC/CJ | Due 2006/10/23 |
Modulator requirements | DFB | Due 2006/07/31 |
Modulator tip-tilt tests | JC | Due 2006/09/25 |
Signal-to-noise calculation | JSY | Due 2006/10/09 |
Slide tests Phase 2 (2 slides, OPD repeatability) | CP | Due 2006/10/16 |
Imaging speed calculation | JSY | Due 2006/10/23 |
Costing | JSY | Due 2006/10/23 |
Final Report | JSY | Due 2006/11/06 |
Preliminary design for downselected concept | FB/JC | Due 2006/11/27 |
to:
ID | Milestone | Person(s) | Due Date | Status |
1 | Beam size memos | DFB | | Delivered |
2 | Generic Switchyard Requirements | JC | | Delivered |
3 | Devise slide tests | CJ | | Complete |
4 | Survey of commercial slides | CP | | Complete |
5 | Generic Detector Requirements | JSY | | Delivered |
6 | P4S combiner optimization | JC | | Complete |
7 | P4S switchyard optimization | JC | | Complete |
8 | P8 combiner optimization | JC | | Complete |
9 | P8 (internal) switchyard optimization | JC | | Complete |
10 | P4/P8 manufacturer dialogue | JC | Due 2006/07/31 | 70% done |
11 | P4S/P8 spectrograph optimization | CJ | Due 2006/09/01 | 70% done |
12 | I4S combiner optimization | FB | Due 2006/07/17 | 90% done |
13 | I4S switchyard optimization | JC | | 80% done |
14 | I6 combiner optimization | FB | Due 2006/07/17 | 90% done |
15 | Optical interface with fringe tracker | JC/CJ | Due 2006/08/14 | 80% done |
16 | Slide tests Phase 1 (1 slide, tip-tilt repeatability) | CP | Due 2006/08/14 | Complete |
17 | Spatial filter evaluation | MCE | Due 2006/09/11 | 50% done |
18 | Alignability evaluation | JC/CJ | Due 2006/10/23 | 10% done |
19 | Modulator requirements | DFB | Due 2006/07/31 | 0% done |
20 | Modulator tip-tilt tests | JC | Due 2006/09/25 | 20% done |
21 | Signal-to-noise calculation | JSY | Due 2006/10/09 | 30% done |
22 | Slide tests Phase 2 (2 slides, OPD repeatability) | CP | Due 2006/10/16 | Awaiting slide |
23 | Imaging speed calculation | JSY | Due 2006/10/23 | Waiting on 21 |
24 | Costing | JSY | Due 2006/10/23 | Waiting on 10 |
25 | Final Report | JSY | Due 2006/11/06 |
26 | Preliminary design for downselected concept | FB/JC | Due 2006/11/27 |
March 09, 2007, at 05:06 PM
by John Young - Original milestones from workpackage definition
Added lines 3-30:
Milestone | Person(s) | Status |
Beam size memos | DFB | Delivered |
Generic Switchyard Requirements | JC | Delivered |
Devise slide tests | CJ | Complete |
Survey of commercial slides | CP | Complete |
Generic Detector Requirements | JSY | Delivered |
P4S combiner optimization | JC | Complete |
P4S switchyard optimization | JC | Complete |
P8 combiner optimization | JC | Complete |
P8 (internal) switchyard optimization | JC | Complete |
P4/P8 manufacturer dialogue | JC | Due 2006/07/31 |
P4S/P8 spectrograph optimization | CJ | Due 2006/09/01 |
I4S combiner optimization | FB | Due 2006/07/17 |
I4S switchyard optimization | JC | Complete |
I6 combiner optimization | FB | Due 2006/07/17 |
Optical interface with fringe tracker | JC/CJ | Due 2006/08/14 |
Slide tests Phase 1 (1 slide, tip-tilt repeatability) | CP | Due 2006/08/14 |
Spatial filter evaluation | MCE | Due 2006/09/11 |
Alignability evaluation | JC/CJ | Due 2006/10/23 |
Modulator requirements | DFB | Due 2006/07/31 |
Modulator tip-tilt tests | JC | Due 2006/09/25 |
Signal-to-noise calculation | JSY | Due 2006/10/09 |
Slide tests Phase 2 (2 slides, OPD repeatability) | CP | Due 2006/10/16 |
Imaging speed calculation | JSY | Due 2006/10/23 |
Costing | JSY | Due 2006/10/23 |
Final Report | JSY | Due 2006/11/06 |
Preliminary design for downselected concept | FB/JC | Due 2006/11/27 |
March 09, 2007, at 03:31 PM
by John Young -
Changed lines 1-2 from:
Workpackage Definition: (Attach:)downselect_defn.pdf
to:
March 09, 2007, at 03:30 PM
by John Young -
Changed lines 1-2 from:
to:
Workpackage Definition: (Attach:)downselect_defn.pdf
March 09, 2007, at 03:04 PM
by John Young -
Added lines 1-2:
March 09, 2007, at 01:05 PM
by John Young -
Added lines 1-6:
The following beam combiner concepts are being considered:
|