Документ взят из кэша поисковой машины. Адрес оригинального документа : http://hea.iki.rssi.ru/SXG/news/clean_tent/images1.html
Дата изменения: Wed Feb 18 14:46:51 2004
Дата индексирования: Mon Oct 1 23:51:33 2012
Кодировка:

Поисковые слова: dust
IKI test facilities

Status of clean tent integration and preparation
to complex tests of flight scientific payload of
Spectrum-X-Gamma mission at IKI test room

December 10,1998 - Laminar flow units were integrated to the clean tent at IKI test area.

November 15,1998 - Integration of the Clean tent at IKI test area is finished.

September 25,1998 - the clean tent laminar flow units (fLeicester University, UK) are put at IKI test room.

August 28,1998 - the clean tent supporting structure is assembled

August 6, 1998 - integration of the bottom level of the clean tent supporting structure


Last updated Nov. 16, 1998 by V.Arefiev, gita@hea.iki.rssi.ru