Документ взят из кэша поисковой машины. Адрес оригинального документа : http://www.eso.org/projects/dfs/team/integration-acceptance.html
Дата изменения: Wed Apr 13 18:07:50 2005
Дата индексирования: Sun Apr 13 22:51:15 2008
Кодировка:

Поисковые слова: релятивистское движение
DFS commissioning: integration acceptance meeting
 [ ESO ]

DFS Department
The QA rules applicable to DFS Commissioning


The Integration Acceptance : meeting during which the Integration phase is assessed and objectives defined during the Integration Kick-Off are checked.


WHEN : typically 3 weeks before the official deadline , i.e. date by which the new DFS release has to be operational on the mountain.

WHAT :
Determine if the coverage of performed tests is adequate :

Check all test results :

Analyze the documentation to be delivered to the mountain (new version of the User's Manual, Intallation guide, ...) : comments from SEG testers or from the QA manager.

Review the complete list of testcases to be re-run on the mountain during the Installation phase (extracted from the current testcases definition).


WHY : check that the integration protocol defined between DFS projects and SEG has been applied.

HOW: Integration Acceptance meeting at DFS level with: If needed, specific Integration acceptance meetings at DFS project level and SCCB meetings may be organized to prepare this Integration acceptance meeting.

Before this meeting,
the SEG testers and the QA manager will prepare a document describing :
a summary of the performed tests : how many testcases effectiveley performed / expected testcases.
list of features / functionalities / performance requirements which are NOT fulfilled.
list of new bugs or new change requests raised during this Integration phase.
list of previous bugs which can be considered as fixed.
list of testcases to be re-run on the mountain.

The QA manager will prepare :
a count of critical, serious and minor bugs (same for change requests) raised during the Integration phase.


The current Commissioning Plan will be updated after this meeting (usually by the QA manager).

It is strongly recommended that each participant prepares the Integration Kick0off meeting before going to it, in order to save time.


 [Project and Developments]  [Overview page for this document]  [ESO]  [Index]  [Search]  [Help]  [News]