Procedure to Install the 2.5m Wind Baffle

Procedure to Install the 2.5m Wind Baffle

Prepared by Russ Owen
Reviewed by French Leger
Maintained by Russ Owen
Last modified on


Cautionary Notes


Equipment Required


Initial State of Telescope


Procedure

  1. Read through the procedure. Make sure you understand all of it before you begin.

  2. Make sure an e-stop is engaged.

  3. Remove the wind baffle from its weather protective covering (tent or tarp).

  4. Roll the wind baffle into the enclosure.

  5. Bolt the wind baffle to the support frame, using the hydraulic jacks to aid in alignment.

  6. Remove the wheels from the wind baffle.

  7. Install the flat field petals.

  8. Install all wires attached to the wind baffle.

  9. Check the balance of the wind baffle plus telescope (the two are turnbuckled together and act as a unit):

    1. Attach the wind baffle pendant control.

    2. Station one person in the lower level to watch the torque reading on the wind baffle altitude motor amplifier.

    3. Make sure the wind baffle tie-down strap allows approximately one foot of motion.

    4. Remove the west jackscrew (the one preventing the wind baffle from going up).

    5. Release all e-stops.

    6. Release the altitude brake.

    7. Move the wind baffle slightly up and down. The torque reading (which is in percent) should be no higher than 60 in both directions. If it is higher, press an e-stop and rebalance the telescope.

    8. Engage an e-stop.

  10. Remove the wind baffle tie-down strap and the jackscrews.

  11. Release all e-stops and raise the wind baffle and telescope to zenith. Monitor the torque as you go: if it exceeds 80, engage an e-stop and rebalance the system.

  12. Pin the telescope at zenith. Pushing the pin in engages an e-stop, so if the pin jams you'll have to use the turnbuckles (not the pendant) to free it.

  13. Install the lower light baffles.

  14. Remove the two turnbuckles attaching the wind baffle to the PSS.

  15. Remove the wind baffle pendant control.

  16. Run the counterweights up to ? to balance the telescope.

  17. Verify proper operation by using Menu or the TCC to drive the telescope. Monitor the wind baffle torque.

  18. Stow all equipment, including:

    1. Wind baffle pendant control in the 2.5m enclosure.

    2. Wind baffle wheels in the 2.5m storage trailer.

    3. Hydraulic jacks in the 3.5m enclosure ground level.

    4. Jackscrews in the 3.5m enclosure ground level.


Document History

2002-03-07 R. Owen. First public release.
2002-03-22 G. Van Doren. Add header and time stamp; verify links