CATWALK INSTALLATION: AUGUST 18, 1999

The catwalk is being installed to provide access to the soon-to-be new HVAC/environmental infrastructure.


Aug. 17: the preparation for the installation of the new catwalk included cutting the tiedowns for the pier grating and providing support straps for the utility pipe.

 

Aug. 18: the catwalk arrives on the truck/crane which is used to maneuver the catwalk into place

The crew from Basin Pipe and Metal (local Alamogordo business) sets up the safety barrels around the work area and begins to offload the catwalk.

The crew hoists the catwalk over the pier railing and lowers the walkway to the ground below.

Later that afternoon, and with many welds and cuts, the crew mounts the catwalk and squares it "plumb" with the pier and the building.

Aug. 19: the installation was completed yesterday. The hand railings and treads for the stairs are to be installed, as well as additional tiedowns.